Lynas Rare Earths
Jagcor is the main civil contractor for Lynas’s $800m Kalgoorlie Processing Facility. Jagcor has worked closely with Lynas over the past 24 months, overcoming design and constructability issues to deliver a quality project and considerable cost savings for the client. Savings and synergies were also extracted by combining both the concrete supply and install packages under a single contract with Jagcor. Works are set to be completed in Q4 2023, with total concrete volumes of approximately 28,000 m3. This included 8,000m3 of concrete with Caltite additive. Jagcor was also able to supply other contractors on site with concrete and stabilised sand – optimising overall project efficiency, and also had on-site NATA accredited concrete and soil testing facilities. Major concrete structures completed by Jagcor included the 4000m3 Kiln and the 3000m3 Filter Building.