Liontown Resources
Late 2022 – In progress
In late 2022, Jagcor was awarded the concrete supply and install package for Liontown Resources Kathleen Valley – Lithium Tantalum Project. Work is progressing well, and completion is scheduled for Q4 2023. Jagcor’s scope includes the construction of large concrete structures for the main processing plants – including mill base, Primary Crusher ROM Wall and Fine Ore Bin Suspended slab. A total of approximately 11,000m3 of structural concrete will be supplied, delivered, and installed for the project. Conditions and specifications were challenging – especially given the prevalence of hard rock and the 2500LM of micro-piling requirements for concrete foundations. Peak manning was over 100 workers.